house 9.11.07
The house with its front windows in.
Date: 09/11/2007
Views: 111
|
attaching mesh
Attaching the mesh for the stucco.
Date: 09/11/2007
Views: 25
|
house 9.12
The Wednesday house front 9/12. The dormer is being worked on.
Date: 09/12/2007
Views: 33
|
|
house 9.13
The Thursday house front. The dormer windows are in.
Date: 09/13/2007
Views: 36
|
stucco spaces
Here you can see the "layout" of elements on the West face.
Date: 09/12/2007
Views: 37
|
Stuccoscratchwest
The scratch coat of stucco has been applied to the West face.
Date: 09/13/2007
Views: 43
|
|
stuccostartbrown
The started the "brown" coat, the second of three layers. They have tinted the cement to the color we chose for the top coat so we can see what it looks like in place.
Date: 09/15/2007
Views: 38
|
stuccobrowncoatwest
The finshed brown coat. It'll take 7 to 10 days for the cement to dry out to its final color.
Date: 09/18/2007
Views: 37
|
stuccoheaderdetail
This is the header detail that is going over the first floor windows.
Date: 09/18/2007
Views: 35
|